The TS Power Plant (TSPP) is a 242 MW gross coal fired power plant designed to operate base loaded. The plant is new and began commercial operations in June 2008. Due to high volumes of snow fall in the northwest the availability of low cost hydropower in 2009 reduced power demand from TSPP and other coal based generating stations. Moreover in 2009 natural gas prices fell to the lowest point in years making energy from newer more efficient combined cycle power plants very favorable. This paper examines the performance of TSPP under varying load output conditions with regard to.
机译:TS电厂(TSPP)是一个242兆瓦的燃煤电厂,旨在运行基本负荷。该电厂是新电厂,于2008年6月开始商业运营。由于西北地区大量降雪,2009年低成本水电的可用性降低了TSPP和其他煤电厂的电力需求。此外,2009年天然气价格跌至多年来的最低点,这使得来自新型高效联合循环电厂的能源非常有利。本文考察了TSPP在变化的负载输出条件下的性能。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号