Numerical analysis of a 36 m deep diaphragm wall - parametric study

机译:36 m深连续墙的数值分析-参数研究。

获取原文

摘要

Last year a deep excavation for the construction of a metro station in Warsaw was executed in complex geotechnical conditions. In the first stage of the investment process the primary soil investigation was performed. Basing on the results of this investigation calculations of supporting system and the design of casing were carried out. In the subsequent investment stages complementary soil investigations were performed and the results were taken into account in the final analysis, design and dimensioning. Significant differences were observed in the results of analysis made at each investment stage. In the paper, description of the case and multiple numerical analysis of the case with variation of soil parameters are presented. The discussion of calculation results in relation to the changing geotechnical data is presented. At the end comparison of theoretical displacements and the displacements of the wall measured on site is given and final conclusions are provided.
机译:去年,在复杂的岩土条件下,对华沙地铁站的建设进行了深挖。在投资过程的第一阶段,对土壤进行了初步调查。根据调查结果,进行了支撑系统的计算和套管的设计。在随后的投资阶段,进行了补充土壤调查,并在最终分析,设计和确定尺寸时考虑了结果。在每个投资阶段进行的分析结果中都观察到了显着差异。本文介绍了这种情况的描述以及随着土壤参数变化而进行的多种数值分析。讨论了与不断变化的岩土数据有关的计算结果。最后比较了理论位移和现场测量的墙位移,并提供了最终结论。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号