High Altitude Mine Waste Remediation - Implementation of the Idarado Remedial Action Plan

机译:高海拔矿山废物整治-Idarado整治行动计划的实施

获取原文

摘要

The Idarado Mine in Colorado's San Juan Mountains includes 11 tailings areas, numerous waste rock dumps, and a large number of underground openings connected by over 100 miles of raises and drifts. The tailings and mine wastes were generated from different mining and milling operations etween 1875 and 1978. The Idarado Remedial Action Plan (RAP) was an innovative 5-year program developed for remediating the impacts of historic mining activities i nthe San Miguel River and Red Mountain Creek drainages. The challenges during implementation included seasonal access limitations due to the high altiutde construction areas, high volumes of runoff during snow melt, numerous abandoned underground openings and stoped-out veins, and high profile sites adjacent to busy jeep trails and a major ski resort town. Implementation of the RaP has included pioneering efforts in engineering design and construction of remedial measures. Innovative engineering designs included direct revegetation techniques for the stabilization of tailings piles, concrete cutoff walls and french drains to control subsurface flows, underground water controls that included pipeliens, weeplines, and portal collection systems, and various underground structures to collect and divert subsurface lows often exceedign 2,000 gpm. remote work locations have also required the use of innovative construction techniques such as heavy lift helicopters to move construction materials to mines above 10,000 feet. This paper describes the 5-year implementation program which has included over 1,000,000 cubic yards of tailing regrading, application of 5,000 tons of manure and 26,000 tons of limestone, and construction of over 10,000 feet of pipeline and approximately 45,000 feet of diversion channel.
机译:科罗拉多圣胡安山脉的Idarado矿包括11个尾矿区,众多废弃物倾倒,以及大量的地下开口,超过100英里的饲养和漂移。尾矿和矿井废物是从不同的采矿和铣削行动产生的,Etween 1875年和1978年。伊达拉多补救行动计划(RAP)是一个创新的5年计划,用于修复历史挖掘和红山的历史矿业活动的影响溪流排水。实施过程中的挑战包括季节性施工区域,雪熔化期间高径流,众多废弃的地下开口和堵塞静脉,毗邻忙碌的吉普车小径和主要的滑雪胜地镇,以及一座主要的滑雪胜地休息区,遇到季节性进出限制。说唱的实施包括工程设计和修复措施建设的开拓努力。创新的工程设计包括尾矿桩稳定,混凝土截止墙和法国排水管的直接植被技术,以控制地下流量,包括管道,WEEPLINE和门户收集系统的地下水控制,以及各种地下结构来收集和转移地下低点非常缩短2,000 GPM。遥控器件还要求使用更新的施工技术,如重型升降机直升机,将建筑材料移动到10,000英尺以上的矿区。本文介绍了5年的实施方案,其中包括超过1,000,000立方码的尾巴尾矿,适用5000吨粪便和26,000吨石灰石,并建造超过10,000英尺的管道和大约45,000英尺的转移渠道。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号