When the shield machine launching or arriving is under construction in the shield tunnel construction, firstly the built retaining structure (piles in a row, diaphragm wall, etc.) of the shield tunnel portal needs to be excavated manually by tradition method, and then the shield machine launch or arrival construction is carried out. Consequently, after the built retaining structure of shield tunnel portal is excavated, it has become a key issue to ensure the soil stability of the work shaft portal for a period of time before the rotary cutter head of shield machine penetrating into or drilling through the stratum. Based on the project case, the principle of high pressure spiral jet grouting, the grouting parameters and the construction technology about dual pipe high-pressure spiral jet grouting piles for reinforcing the soil of the end well portal are discussed in this paper. Furthermore, some suggestions are put forward on the questions that exist in the jet grouting piles for the shield launching or arrival construction.
机译:当在盾构隧道施工中正在施工的盾构机发射或到达时,首先需要通过传统方法手动开挖盾构隧道门的已建固定结构(成排的桩,隔板墙等),然后再进行施工。进行盾构机发射或到达施工。因此,在开挖盾构隧道门的固定结构之后,在盾构机的旋转刀头钻入或钻穿地层之前的一段时间内,确保工作井门的土壤稳定性已成为关键问题。 。根据工程实例,讨论了高压螺旋旋喷灌浆的原理,双管高压螺旋旋喷灌浆桩的注浆参数和施工技术,以加固端井孔道的土壤。此外,针对盾构发射或进场施工的旋喷桩存在的问题提出了一些建议。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号