Case Study—A State of the Art, Reinforced Soil Slope System for Runway End Safety Area at Kannur International Airport, India

机译:案例研究—印度坎纳努尔国际机场跑道末端安全区的最先进加筋土坡系统

获取原文

摘要

Kannur International Airport is a green field airport project with airside development on a hilly terrain plateau. The airside infrastructure development works involved earthworks of 45.5 million cum in cutting and filling. To accommodate the desired runway length and runway end safety area (RESA), the plateau was extended along the runway centreline, beyond the plateau, and therefore requiring a high embankment filling with height ranging from 66 m to 87 m. Since the available land was insufficient to accommodate the construction of embankment with a free slope; a reinforced soil slope (RSS), with maximum slope of 65 degrees, was designed and constructed. An RSS of this magnitude in the runway alignment for an airport is a unique feature of this project, located in high rainfall area. The geometry of the RSS itself was challenging being asymmetrical with curves and bends. The airport operational perimeter (AOP) road is positioned at approximately mid height of the high embankment. The slope was reinforced with high strength uniaxial geogrids and the complete system was designed using finite element analysis. Slip circle failure and wedge failure cases were considered in both static and seismic analysis for local and global failure cases. Considering the high annual rainfall received at the airport site, an elaborate drainage system was also designed for the RSS embankment. The paper presents a case study detailing the concept to design development of the high RSS system constructed for providing the planned runway length and RESA.
机译:坎努尔国际机场是一个绿色领域的机场项目,其空侧开发位于丘陵地带的高原上。空侧基础设施的开发工作涉及4,550万立方米的土方工程,涉及挖方和填方。为了适应所需的跑道长度和跑道末端安全区域(RESA),高原沿跑道中心线延伸,超过了高原,因此需要高路堤填充物,高度范围为66 m至87 m。由于可用土地不足以容纳有自由坡度的堤防建设;设计并建造了最大坡度为65度的加筋土坡(RSS)。该机场位于跑道高处的RSS数量巨大,是该项目的一个独特功能,它位于高降雨地区。 RSS本身的几何形状具有挑战性,因为它与曲线和折弯不对称。机场运行周界(AOP)道路位于高路堤的大约中间高度。用高强度单轴土工格栅加固了边坡,并使用有限元分析设计了完整的系统。在局部和整体破坏案例的静态和地震分析中都考虑了滑移圈破坏和楔形破坏案例。考虑到机场现场每年的高降雨,还为RSS路堤设计了精心设计的排水系统。本文提供了一个案例研究,详细介绍了设计用于提供计划的跑道长度和RESA的高RSS系统的设计开发概念。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号