首页> 外文会议>International Conference on Material Science and Engineering >Analysis of Flying Rock for Demolition of Cooling Tower Made by Reinforced Concrete Materials in the Method of FTA
【24h】

Analysis of Flying Rock for Demolition of Cooling Tower Made by Reinforced Concrete Materials in the Method of FTA

机译:钢筋混凝土材料拆除岩岩拆除岩石的拆迁分析

获取原文

摘要

In order to fully prevent flying rocks casting to surrounding constructions in blasting demolition project, fault tree analysis was used for safety evaluation. The analysis and calculation of minimal cut sets and structure importance indicates that the highest probability of flying rock accidents is caused by large quantity of maximum priming charge. And other events come second but cannot be ignored. Thus, several measures were adopted according to the analysis result and the final blasting result showed that no flying accidents happened in the whole process.
机译:为了完全防止爆破拆除项目的周围结构的飞行岩石,故障树分析用于安全评估。 最小切割和结构重要性的分析和计算表明,飞行岩会事故的最高概率是由大量最大灌注电荷引起的。 而其他事件是第二个,但不能被忽视。 因此,根据分析结果采用了几种措施,最终的爆破结果表明,整个过程中没有发生任何飞行事故。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号