This paper presents a bored cast-in-place concrete piling case history for the port facility of an aluminum smelter project in the Middle East. The port facility is coastal with subsurface conditions consisting of reclamation fill, underlying sand, and deeper weathered rock (intermediate geomaterial). A geotechnical investigation of the port facility mainly included borings, cone penetration tests, and laboratory testing of soil and weathered rock samples. Six pre-production piles were load-tested axially using Osterberg load cells and laterally using a reaction system. Two production piles were also axially load (proof) tested using the conventional top load method with a reaction frame and kentledge. Load test results and capacity analyses are discussed. The results of settlement monitoring of completed structures are also presented. In total, 750 production piles in two diameters, 600 mm and 1,000 mm, were installed. Both the smelter facility and the port facility are constructed and operating satisfactorily.
机译:本文介绍了中东一家铝冶炼厂的港口设施的无聊现浇混凝土打桩案例。港口设施位于沿海,具有地下条件,包括填海填埋,下层沙子和更深的风化岩石(中间土工材料)。港口设施的岩土工程调查主要包括钻孔,圆锥体渗透测试以及土壤和风化岩石样品的实验室测试。使用Osterberg称重传感器轴向测试了六个预生产桩,使用反应系统横向测试了六个。还使用常规的顶部加载方法(带有反应架和kentledge)对两个生产桩进行了轴向载荷(抗力)测试。讨论了负载测试结果和容量分析。还介绍了已完成结构的沉降监测结果。总共安装了750个生产桩,两个直径分别为600 mm和1,000 mm。冶炼厂和港口设施的建设和运营均令人满意。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号