The desulfuration system in the second phase project of Sanhe Power Plant is the first such system that adopts in-duct FGD with no-bypass design by domestic power plants.Different from that of the conventional FGD with bypass design,a running control mode,which is important for the security of the absorbing tower within the designed ranges,shall be made to ensure the flue gas temperature and dust concentration at the inlet of the absorbing tower.The stable running of the system shows that the control mode is feasible.