根据"以可靠性为中心的检修(RCM)"思想,提出通过分析不同设备对系统供电可靠性的影响大小,来确定设备的检修时序,从而为检修计划的优化制订提供决策依据.该方法比其他类似方法更直接,需要的可靠性参数最少,计算最简单,计算效率最高.实际工程应用案例表明,该方法能够有效应用于配电网检修计划的优化,具有良好的科学性和实用性.%Based on the concept of "reliability-centered maintenance"(RCM),this paper introduces a method of determining time sequences for equipment maintenance by analyzing the impact of different equipment on the power supply reliability of the distribution network system,which is helpful in making strategic decisions for the optimization of the maintenance scheduling.Compared with similar methods,this one has such advantages as its directness,fewest reliability parameters needed,simplest computation and highest computational efficiency.Its application in real projects has proved its effectiveness in the optimization of the maintenance scheduling for the distribution network as well as its good scientificalness and practicability.