首页> 中文期刊> 《电子科技学刊》 >Live-Grid Operation and Maintenance of the 35 kV/121 MVA Superconducting Cable System

Live-Grid Operation and Maintenance of the 35 kV/121 MVA Superconducting Cable System

         

摘要

A 33.5 m, 35 kV/121 MVA, three-phase, warm dielectric HTS power cable system was successfully installed and activated in China Southern Power Grid at the Puji substation in Kunming on April 19th of 2004, supplying electricity to four industrial customers (including two metallurgical refineries) and a residential population of about 100000. In this paper, we give an update on the operation and maintenance status of the system and comments on reliability issues. We conclude that the superconducting cable system is currently quite robust and feasible for particular utility applications, and it will be improved by advancement in cryogenic equipment and system technology.