Taking the loading measurement analysis of now-poured structure of floor formwork support in some project as the example,the paper makes the vertical pole loading deformation supervision scheme,concludes the results of the formwork vertical pole loading test by the theoretic calculation,and has relative conclusion by the analysis and research,so as to direct the field construction effectively.%以某工程现浇结构楼板模板支撑荷载测试为例,制定了立杆荷载变形监测方案,通过理论计算得出模板支撑立杆荷载测试结果,并经分析研究得出相关结论,以期有效指导现场施工。