This paper expounds the design parameters of exposed stone cement concrete pavement in high anti-slide tunnel, analyzes the spraying time, spraying dose, washing time and so on, and according to the actual pavement construction processing requirements, the paper describes the design parameters of the concrete pavement with exposed stone, including the spraying time, the spraying dose, the washing time and so on. In view of the common problems, the corresponding technical solutions are put forward to promote the construction technology development of exposed stone cement concrete pavement in high anti-slide tunnel.%结合具体工程案例,对高抗滑隧道露石水泥混凝土路面设计参数进行阐述,从露石剂喷洒时间、喷洒剂量、冲洗时间等方面进行分析,依据实际路面施工处理要求,针对常见问题,提出了相应的技术解决办法,进而推进高抗滑隧道露石水泥混凝土路面施工技术发展.