为防止腐蚀性烟气进一步侵蚀防腐涂层,确保排烟冷却塔后续运行的安全性和可靠性,须对冷却塔的防腐涂层进行维修。为达到此目标,在防腐维修施工过程中,必须采取有效方法严格控制各个技术环节的施工质量。本文即针对某电厂排烟冷却塔防腐维修工程,采用工程质量控制ABC法,以确保顺利完成防腐维修的任务。同时探讨冷却塔防腐维修施工质量控制过程中存在的问题。%In order to prevent corrosion of the anticorrosive coating, and ensure safety and reliability of the cooling tower, the anticorrosion coating of cooling tower is required for maintenance after 8 years' operation. In order to achieve this goal, we must take effective methods to control the construction quality of the various technical processes. This article aims at using the engineering quality control ABC method to ensure the smooth completion of the anti-corrosion maintenance task. At the same time, the existing problems in the construction quality control of cooling tower anticorrosion maintenance are discussed.