The equipment floor of vertical ship -lift machine of Shatuo Hydropower Station is designed as a beam -slab struc-ture, so its concrete construction is encountered with many difficulties such as layout of lifting machine , construction interfer-ence, etc.And the full framing support for template would take a large quantity of human power and material resources , and pro-long the construction period .By using bailey beam , the assembling work was reduced and the construction interference was effec-tively avoided, which was beneficial to the quick construction , and the technical -economic indexes were optimized to the ulti-mate degree .The installation and removal process of the bailey beam system as well as the concrete construction solution are in -troduced , which could provide a reference for similar projects .%沙沱水电站垂直升船机的设备层为板梁结构,其混凝土浇筑施工面临起重设备布置、施工干扰多等困难,若采用满堂钢管排架作模板支撑,则需耗费大量人力物力,且拖延工期。通过采用贝雷梁技术,不仅使搭建工作量及施工干扰也减少,且有利于快速施工,其综合技术经济指标达到了最大限度的优化。简要介绍了贝雷梁系统的安装与拆除思路及混凝土施工方案等。