Commissioning after major rebuilds and new constructions

机译:大型改建和新建工程后进行调试

获取原文
获取原文并翻译 | 示例
           

摘要

Commissioning is often the most difficult part of a capital project because although it is almost always possible to construct a plant, until it is complete there will always be some uncertainties about how a one-off system will behave. Unfortunately, planning for commissioning is rarely as thorough as for other stages of the project and there is always pressure to get the finished plant on-line as soon as possible. Further, in many organisations there are a limited number of people with experience of commissioning, because large projects are infrequent.rnTogether these factors often lead to inefficient and even damaging strategies being applied.rnThis paper discusses strategies and the development of skills that will usually result in more effective commissioning.
机译:调试通常是基本建设项目中最困难的部分,因为尽管几乎总是可以建造工厂,但在建成之前,对于一次性系统的运行方式始终存在一些不确定性。不幸的是,调试计划很少像项目其他阶段那样详尽,并且总是存在使尽快完成工厂投产的压力。此外,在许多组织中,由于大型项目很少发生,因此只有少数人具有调试经验.rn这些因素通常会导致应用效率低下甚至是破坏性的策略。本文讨论了通常会导致的策略和技能发展以更有效地进行调试。

著录项

  • 来源
    《Appita》 |2010年第5期|p.347-353|共7页
  • 作者单位

    Covey Consulting Pty Ltd, 660 High Street, Kew East, Victoria, 3102, Australia;

    rnCovey Consulting Pty Ltd, 660 High Street, Kew East, Victoria, 3102, Australia;

    rnCovey Consulting Pty Ltd, 660 High Street, Kew East, Victoria, 3102, Australia;

    rnCovey Consulting Pty Ltd, 660 High Street, Kew East, Victoria, 3102, Australia;

  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号