首页> 外文期刊>Procedia CIRP >Two-stage Sequence Generation for Partial Disassembly of Products with Sequence Dependent Task Times
【24h】

Two-stage Sequence Generation for Partial Disassembly of Products with Sequence Dependent Task Times

机译:具有阶段相关任务时间的部分分解产品的两阶段序列生成

获取原文
           

摘要

For disassembly sequence generation, partial disassembly and sequence dependent task times are typically not considered together in the same model. We developed a two-stage optimization program that first determines the optimal partial disassembly sequence according to reuse value only, followed by the second stage that finds the optimal partial disassembly sequence that also includes sequence dependence task times. We prove the optimality of the two-stage approach under the condition that all components with any positive reuse value must be included in the final sequence. If this condition does not need to be met, a task hedging policy is shown to be effective.
机译:对于拆卸序列的生成,通常不会在同一模型中一起考虑部分拆卸和与序列相关的任务时间。我们开发了一个两阶段的优化程序,该程序首先仅根据重用值确定最佳的部分拆卸顺序,然后进行第二阶段的查找最佳的部分拆卸顺序,该顺序还包括与序列相关的任务时间。我们证明了在所有具有任何正重用值的组件都必须包含在最终序列中的情况下,两阶段方法的最优性。如果不需要满足此条件,则表明任务对冲策略是有效的。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号