Commonwealth Edison Must Source Power From FutureGen Plant, Illinois Court Affirms

机译:伊利诺伊州法院确认英联邦爱迪生必须从FutureGen工厂获得电力

获取原文
获取原文并翻译 | 示例
           

摘要

An Illinois appeals court ruled the state's primary utility regulator holds authority to compel electric utilities to enter into sourcing agreements with FutureGen Industrial Alliance Inc., which hopes to construct a near zero-emission coal-fired power plant in Southern Illinois (Commonwealth Edison Co. v. Ill. Commerce Comm'n, Ill. App. Ct., No. 2014 App. 1st 130544, 7/22/14). The First District Illinois Court of Appeals on July 22 affirmed an order of the Illinois Commerce Commission (ICC) requiring Commonwealth Edison Co. to source electric power from the proposed FutureGen 2.0 facility in Meredosia, Ill.
机译:伊利诺伊州上诉法院裁定,该州的主要公用事业监管机构有权迫使电力公用事业与FutureGen Industrial Alliance Inc.签订采购协议,该公司希望在伊利诺伊州南部建造一座近零排放的燃煤电厂(英联邦爱迪生公司。 v。Ill。Commerce Comm'n,Ill。App。Ct。,No. 2014 App。1st 130544,7/22/14)。伊利诺斯州第一区上诉法院于7月22日确认了伊利诺伊州商务委员会(ICC)的一项命令,该命令要求英联邦爱迪生公司从位于伊利诺伊州Meredosia的拟议FutureGen 2.0设施中获取电力。

著录项

相似文献

  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号