Serbia's state-owned power utility Elektroprivreda Srbije (EPS) announced on 4 July that it has signed a contract with Power Machines of Russia to complete the rehabilitation of the Iron Gates (Derdap) 1 hydro plant on the river Danube. Power Machines will carry out the upgrade of the A2 turbine from this September for completion in October 2019, followed by that of the A3 turbine, and will complete the entire project in January 2021, EPS announced.
机译:塞尔维亚国有电力公司Elektroprivreda Srbije(EPS)于7月4日宣布,它已与俄罗斯Power Machines签署了一项合同,以完成多瑙河上Iron Gates(Derdap)1水电站的修复。 EPS宣布,Power Machines将从今年9月开始对A2涡轮机进行升级,并于2019年10月完成升级,随后将对A3涡轮机进行升级,并将于2021年1月完成整个项目。