Study of relationship between cost overrun and labour productivity in road construction projects

机译:道路建设项目成本超支与劳动生产率的关系研究

获取原文
获取原文并翻译 | 示例
           

摘要

This study aims at examining the relationship between cost overrun and labour productivity. To do so, a questionnaire survey was used to elicit the attitude of consultants and contractors towards the factors affecting cost overrun and labour productivity in road construction projects in the West Bank. The study has established that among the various factors that causes cost overrun, awarding the bid to the lowest price, poor planning in early stages of the project, and financial status of the owner top the list. The respondents' input revealed that the most significant factors affecting labour productivity are: lack in materials, inaccurate drawings and specifications, and lack of labour experience. Regression analysis was used to show the impact of labour productivity on cost overrun using data collected from implemented projects in the West Bank. Significant direct relationship was found between cost overrun and labour productivity in base works of road construction projects.
机译:本研究旨在检验成本超支与劳动生产率之间的关系。为此,使用了问卷调查表,以引起顾问和承包商对西岸道路建设项目中影响成本超支和劳动生产率的因素的态度。该研究已经确定,在导致成本超支的各种因素中,以最低价格进行竞标,项目早期阶段的规划欠佳以及所有者的财务状况均位居榜首。受访者的意见表明,影响劳动生产率的最重要因素是:材料短缺,图纸和规格不正确以及劳动经验不足。使用从西岸已实施项目中收集的数据,使用回归分析来显示劳动生产率对成本超支的影响。在道路建设项目的基础工程中,成本超支与劳动生产率之间存在着显着的直接关系。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号