To revamp a blast furnace (BF) is required about every 15 years, and revamp duration by a conventional method is around 130 days. JFE Steel has developed a new revamping method, so called "Large Block Ring Construction Method." By employing the method, the revamp duration was remarkably reduced to a half of a conventional one. A furnace body (10 000 t) was segmented into blocks of 10 t to 20 t weight during dismantling and installation in conventional method. Blocks by the Large Block Ring Constitution Method weigh over 2 000 t a piece. Consequently, the revamp duration of No. 6 BF at East Japan Works(Chiba) in 1998 was only 62 days, which was the world shortest record of revamp duration. The method was also successfully adopted to No. 5 BF at West Japan works (Fukuyama) in 2005, and established a. new world record of 58 days.
机译:大约每15年需要进行一次高炉(BF)的翻新,而采用传统方法进行翻新的时间约为130天。 JFE Steel开发了一种新的改造方法,即所谓的“大块环构造方法”。通过采用该方法,改造持续时间显着减少到传统改造的一半。在按常规方法拆卸和安装过程中,将炉体(10000吨)分成10吨至20吨重的块。大块环构成法生产的块重超过2000吨。因此,1998年日本东日本工厂(千叶)的6号高炉改造时间仅为62天,是世界上改造时间最短的记录。该方法还于2005年在西日本工厂(福山)成功地用于5号高炉,并建立了一个方法。 58天的新世界纪录。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号