Drill and blast excavation is making steady progress in the early phase of underground works on the Cheves hydropower project, under construction in the Andes mountains of Peru. The contractor, Hochtief, leading JV Constructora Cheves, has excavated the adits and access tunnels at key areas of the 9.7km-long headrace, including the surge tunnel, the powerhouse where the crown has already been opened up. It is blasting from the lower section of the 3.3km-long tailrace as well as both ends of the transfer conduit between reservoir high in the catchment area.
机译:秘鲁安第斯山区正在建设的Cheves水电项目地下工程的初期,钻探和爆破开挖正在稳步进行。承包商霍奇蒂夫(Hochtief)率领合资公司Constructves Cheves,在9.7公里长的赛马场的关键区域开挖了平巷和通道隧道,其中包括浪涌隧道,这是已经打开王冠的动力室。它从3.3公里长的尾矿的下部以及集水区高处的储层之间的输送管道的两端爆炸。