Machinex brought a single-stream processing system and various other pieces of equipment on-line at the U.S. Naval Station in Guantanamo Bay, Cuba. Getting it all to the island was one of the biggest challenges, according to a press release, because the project required more than 40 containers. Equipment barges set out for Guantanamo Bay every 2-3 weeks, and there were two naval planes running each week to transport crews. Jerome Lemay, lead project manager for Machinex, said in the press release that "when I first heard of this project and the intricacies involved, I thought it would be a challenge." This project was a partnership between Machinex, HDR and RQ Construction.