首页> 美国政府科技报告 >Formation and sustainment of a very low aspect ratio tokamak using coaxial helicity injection (the Helicity Injected Torus (HIT) experiment). Progress report No. 1, June 1, 1990-January 31, 1991.
【24h】

Formation and sustainment of a very low aspect ratio tokamak using coaxial helicity injection (the Helicity Injected Torus (HIT) experiment). Progress report No. 1, June 1, 1990-January 31, 1991.

机译:使用同轴螺旋注射(Helicity Injected Torus(HIT)实验)形成和维持非常低纵横比的托卡马克。 1990年6月1日至1991年1月31日第1号进度报告。

获取原文

摘要

In this paper we will detail the progress of the Helicity Injected Tokamak experiment construction, including the following components: vacuum vessel and pumping system; helicity source and power supply; toroidal field coil and power supply; bias coil and ...