首页> 外国专利> CONSTRUCTION METHOD OF EARTH RETAINING STRUCTURE OF BASE ROCK LAYER BY GROUT METHOD AND EARTH RETAINING STRUCTURE

CONSTRUCTION METHOD OF EARTH RETAINING STRUCTURE OF BASE ROCK LAYER BY GROUT METHOD AND EARTH RETAINING STRUCTURE

机译:灌浆法和基土支护结构施工基岩土支护结构的方法。

摘要

PROBLEM TO BE SOLVED: To provide a method and an earth retaining structure, excellent in workability, and realizing earth retaining by an open cut, by using a grouting technology.;SOLUTION: A method for constructing an earth retaining structure in a base lock layer part on the flow board side among the periphery of an excavation expected place of a base lock layer, includes (A) a process of boring a first hole row composed of a plurality of substantially vertical pores in parallel to a virtual excavation surface when viewed from above in a part near to the virtual excavation surface between a base lock layer part and the excavation expected place among the base lock layer part, (B) a process of forming a first hardening wall part by injecting a hardening material into the respective pores of these first hole rows, (C) a process of boring a second hole row composed of the plurality of substantially vertical pores in parallel to the virtual excavation surface when viewed from above in a part distant from the virtual excavation surface among the base lock layer part and (D) a process of forming a second hardening wall part of continuing with the first hardening wall part by injecting the hardening material into the second hole row, and constitutes an earth retaining wall by executing the process (D) after hardening the first hardening wall part by executing the process (B) before or after the process (C).;SELECTED DRAWING: Figure 1;COPYRIGHT: (C)2017,JPO&INPIT
机译:解决的问题:提供一种方法和一种土工结构,其具有优异的可加工性,并且通过使用灌浆技术通过明挖实现土的固结。;解决方案:一种用于在基锁层中构造土工结构的方法。在基本锁定层的开挖预期位置的外围中的流板侧的一部分中,包括(A)从虚拟的开挖面观察时平行于虚拟的开挖面而钻出由多个基本垂直的孔构成的第一孔列的工序。在基部锁定层部分与基部锁定层部分之间的预期挖掘位置之间的虚拟挖掘表面附近的部分中,(B)通过将硬化材料注入到各个孔中来形成第一硬化壁部分的过程。在这些第一孔排中,(C)在俯视图中从平行于虚拟挖掘面的方向钻出第二孔排的过程,该第二孔排由多个基本垂直的孔构成(D)通过将硬化材料注入第二孔列而形成与第一硬化壁部连续的第二硬化壁部的工序,其构成为与基体锁定层部中的远离虚拟挖掘面的部分相接。通过在步骤(C)之前或之后执行步骤(B)来硬化第一硬化壁部分,然后通过执行步骤(D)来制造壁。;选定的图纸:图1;版权:(C)2017,JPO&INPIT

著录项

  • 公开/公告号JP2017089183A

    专利类型

  • 公开/公告日2017-05-25

    原文格式PDF

  • 申请/专利权人 TAKENAKA KOMUTEN CO LTD;

    申请/专利号JP20150218766

  • 发明设计人 KOMURA YUICHI;UCHIDA AKIHIKO;

    申请日2015-11-06

  • 分类号E02D17/04;E02D17/20;E02D3/12;

  • 国家 JP