LIFTING CONVEYING METHOD OF MATERIAL IN HIGH-RISE BUILDING WORK
LIFTING CONVEYING METHOD OF MATERIAL IN HIGH-RISE BUILDING WORK
展开▼
机译:高层建筑工程中的物料提升输送方法
展开▼
页面导航
摘要
著录项
相似文献
摘要
PROBLEM TO BE SOLVED: To reduce a conveying time without increasing the number of lifting machines and, at the same time, to make it possible to settle the lack of space in a stock-yard. ;SOLUTION: In construction work of a building, carriers 12 and 16 rising and falling in a temporary path are used to lift and convey finishing materials and equipment work materials to every floor, and stock yards are also provided on an intermediate floor of the building except a material delivery floor in the first floor on the ground. Materials W2 required for every floor higher than the intermediate floor are stocked in bulk in the stock yards.;COPYRIGHT: (C)1999,JPO