为使承包商和发包方双方共担合同价款变动风险,合理控制工程造价,对发承包双方在施工过程中发生重大工程变更或累计变更超过一定幅度的合同价格进行调整的程序及方法进行了详细论述,主要分析了市场价格波动引起的调整措施以及工程变更量价款调整的原则,以供参考。%In order to make the contractor and employer both sharing the contract price changes risk,reasonably control of project cost,discussed in detail the programs and methods of both contractor and employer occurrence of major engineering change or cumulative change over a certain range contract price made adjustment in construction process,mainly analyzed the adjustment measures fluctuation by market price and the princi-ple of engineering change price adjustment,for reference.