结合承接的外资项目工程经验,从概念、人工时和 S 曲线的生成等方面入手,对项目实施阶段的四级进度计划进行了阐述说明,指出采用 S 进度曲线比较法,可直观的比对并判断实际进度与计划进度的差值,进而了解项目的整体运行情况。%Combining with foreign funded project engineering experience,starting from aspects of concept,labor man-hour and S curve genera-tion,the paper describes the four-grade schedule planning at project implementation phase,and points out advantages of S-curve schedule com-parison method,which can tell the difference of actual schedule and planned schedule and know out the integral project operation conditions as well.