首页> 外文期刊>Civil Engineering Surveyor >The death knell tolls for target cost contracts?
【24h】

The death knell tolls for target cost contracts?

机译:死亡knell为目标成本合约收费?

获取原文
获取原文并翻译 | 示例
           

摘要

The ABC case considered the situation where the contractor was in culpable delay, but the court's interpretation of the clause applies to any breach of contract, so if using the NEC and the client has amended clause 11.2 (26) to include the NR12 amendment then it bites. In the real world there are many technical breaches of contract by the contractor, from the simple failure to reply to a communication within the period for reply to the cost of correcting defects before completion and many more. By using this amendment, the risk pendulum has definitely swung away from the client and towards the contractor.
机译:ABC案件认为承包商处于延迟的情况,但法院对该条款的解释适用于任何违约,因此如果使用NEC和客户修订第11.2(26)条包括NR12修正案 咬伤。 在现实世界中,承包商有许多技术违约,从简单的未能回复了在完成之前回复纠正缺陷的成本的沟通以及更多。 通过使用这项修正案,风险摆动绝对远离客户和承包商。

著录项

  • 来源
    《Civil Engineering Surveyor》 |2021年第2期|44-46|共3页
  • 作者

    W J Edwards;

  • 作者单位

    W J Edwards & Associates;

  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号