The second turbine at the Chiem Hoa hydro project on the Gam river in Vietnam's northeastern province of Tuyen Quang province started generating electricity for the national grid on 8 September, following successful testing at the start of the month. The first of the 48 MW plant's three bulb turbines began operation in July, with the third 16 MW unit expected to begin service in November. The plant is the first in Vietnam to use low head bulb turbines. It is projected to generate average annual output of 193.4 GWh.
机译:在本月初成功进行测试后,越南东北部省图扬县(Tuyen Quang)的甘姆河(Gam river)上的Chiem Hoa水电项目的第二台涡轮机于9月8日开始为国家电网发电。该48兆瓦发电厂的三台球形涡轮机中的第一台已于7月开始运行,第三台16兆瓦机组预计于11月开始运行。该工厂是越南首家使用低水头球轮机的工厂。预计将产生193.4 GWh的年平均产量。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号