The Analysis of Factors Affecting Overdue Contract Period of Maloy Sea Port?s Trestle Construction Project in East Kutai Regency, East Kalimantan

机译:基于东·卡泰丹东库泰泰安港的逾期合同因素分析

获取原文
获取原文并翻译 | 示例
           

摘要

The Maloy sea port trestle construction project in East Kutai of East Kalimantan in 2014 has overdue on the average of 15% from the contract period. This study aims to find out the factors that influence the overtime contract period and to reveal the most dominant factor and strategies to overcome the problem. The methodology used here is factor analysis and multiple linear regression analysis toward questionnaires that were distributed to 56 respondents of owner, contractor and supervision consultant who were involved in the project. Based on the result of study with F-test, it is found that human resource (X _( 1 ) ), job implementation method (X _( 2 ) ), timeline (X _( 3 ) ), supervision (X _( 4 ) ), equipment (X _( 5 ) ), work environment (X _( 6 ) ), material (X _( 7 ) ) and finance (X _( 8 ) ) have mutual effect on overtime contract period on the Maloy sea port of trestle construction project in East Kutai of East Kalimantan, F _( count ) = 11.297> F _( table ) = 2.140. However, based on t test partially, the factors that count table significantly influence the overtime contract period on the Maloy sea port of trestle construction project in East Kutai of East Kalimantan are human resources (X _( 1 ) ), material (X _( 7 ) ) and finance (X _( 8 ) ). The most dominant factor is shown by the highest standardized value of $ that is human resources factor (X _( 1 ) ). The strategy to overcome the problem is that the contractor should assign some experts and hire the number of human resources to work based on the skills and needs in carrying out the work and the contractor must have good financial management, regular and timely payment of wages and contractors should send the materials on time, especially, local or non-local materials to the project site.
机译:2014年东卡马丹东库泰泰的Maloy Sea Port Treste建筑项目已逾期,合同期限为15%。本研究旨在找出影响加班合同期并揭示最大主导因素和策略来克服问题的因素。这里使用的方法是对参与该项目的所有者,承包商和监督顾问的56个受访者的问卷的因素分析和多元线性回归分析。基于F-Test的研究结果,发现人力资源(x _(1)),作业实现方法(x _(2)),时间轴(x _(3)),sovingision(x _( 4),设备(x _(5)),工作环境(x _(6)),材料(x _(7))和金融(x _(8))对Maloy的加班合同期具有相互影响东Kalimantan东库的Trestle建筑项目海港,F _(计数)= 11.297> F _(表)= 2.140。但是,根据T检验部分,计数表的因素显着影响东奎丹东库泰丹施泰尔施工项目的Maloy海港的加班合同期是人力资源(X _(1)),材料(X _( 7))和金融(X _(8))。最主要的因素是由人力资源因子的最高标准化值(x _(1))表示。克服问题的战略是,承包商应根据开展工作的技能和需求雇用一些专家并雇用人力资源的数量,并承包商必须具有良好的财务管理,定期支付工资和支付工资承包商应按时,特别是当地或非本地材料发送材料。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号