Tropicana Project Heading for Q4 2013 Production

机译:Tropicana项目标题为2013年第四季度生产

获取原文
获取原文并翻译 | 示例
           

摘要

AngloGold Ashanti reported in late January 2013 that the Tropicana gold project located 330 km east-northeast of Kalgoorlie, Western Australia was on schedule to begin production during the fourth quarter of 2013. Construction was 55.6% complete at year-end 2012. Engineering design and procurement activities were complete, and all major equipment items had been delivered to the site. The Tropicana project is a joint venture between AngloGold Ashanti (70%) and Independence Group NL (30%). Project construction was approved in November 2010. Since that time Tropicana's mineral resource has grown by 2.8 million oz to 7.9 million oz, and the potential for extensions to the known ore zones and the discovery of additional ore within trucking distance of the processing plant remains high.
机译:AngloGold Ashanti于2013年1月下旬报道,位于西澳大利亚州Kalgoorlie东北330公里处的Tropicana金矿项目按计划于2013年第四季度开始生产。2012年年底完工率为55.6%。工程设计和采购活动已完成,所有主要设备项目均已交付到现场。 Tropicana项目是AngloGold Ashanti(70%)和NL Independence Group(30%)的合资企业。项目建设于2010年11月获得批准。自那时以来,Tropicana的矿产资源已增长280万盎司,达到790万盎司,并且扩展到已知矿区的潜力以及在加工厂运输距离之内发现更多矿石的可能性仍然很高。 。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号