Asanko Gold Project's First Phase Targets 190,000 oz/y in 2016

机译:Asanko黄金项目的第一阶段目标是在2016年达到190,000盎司/年

获取原文
获取原文并翻译 | 示例
           

摘要

Asanko Gold has released the Definitive Project Plan for Phase 1 of its two-phase Asanko gold mine project in Ghana. Construction has started on Phase 1, with steady state production planned at 190,000 oz/y. First gold is targeted for the first quarter of 2016 and steady state production for the second quarter of 2016. Phase 1 is slated to produce 2.33 million oz of gold over a 12-year mine life. A study of Phase 2 development is scheduled for completion during the first quarter of 2015 and is based on development of the Esaase deposit 30 km north of the Phase 1 plant site.
机译:Asanko Gold已发布其加纳Asanko金矿两阶段项目第一阶段的最终项目计划。第一阶段的建设已经开始,计划年产量稳定在190,000 oz / y。第一金计划于2016年第一季度投入生产,第一阶段金计划于2016年第二季度进入稳定状态。第一阶段计划在12年的矿山寿命中产生233万盎司的黄金。第二阶段开发的研究计划于2015年第一季度完成,该研究基于第一阶段工厂以北30公里处Esaase矿床的开发。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号