Contractors sue Seattle Tunnel Partners for work completed on TBM repair vault

机译:承包商起诉西雅图隧道合作伙伴完成TBM维修库的工作

获取原文
获取原文并翻译 | 示例
           

摘要

After months of delays on the SR-99 project, the tunnel boring machine (TBM) has now mined 1,036 m (3,400 ft) of the 2,825-m (9,270-ft) tunnel and installed 525 concrete tunnel rings. It seems that troubled project is back on track underground, but above ground, the project continues to face obtacles and one of the latest could eventually play out in a Seattle-area courtroom.
机译:经过SR-99项目数月的延误后,隧道掘进机(TBM)现在已开采了1,036 m(3,400 ft)的2,825米(9,270英尺)隧道,并安装了525个混凝土隧道环。陷入困境的项目似乎又回到了地下轨道,但在地面之上,该项目继续面临障碍,而最新的项目之一最终可能会在西雅图地区的法庭上进行。