首页> 外文期刊>NGW's Gas Market Reconnaissance >NRG Ohio’s plans to build a 20-mile natural gas pipeline to supply NRG Energy’s 734-megawatt Avon Lake power plant on Lake Erie have been conditionally approved by Ohio Power Siting Board, which is part of the Ohio Public Utilities Commission
【24h】

NRG Ohio’s plans to build a 20-mile natural gas pipeline to supply NRG Energy’s 734-megawatt Avon Lake power plant on Lake Erie have been conditionally approved by Ohio Power Siting Board, which is part of the Ohio Public Utilities Commission

机译:NRG Ohio的计划是建设一条20英里长的天然气管道,以向NRG Energy在伊利湖上的734兆瓦的Avon Lake电厂供电,该计划已获得Ohio Power Siting Board的有条件批准,隶属于Ohio Public Utilities Commission

获取原文
获取原文并翻译 | 示例
           

摘要

Construction of the $40 million, 24-inch pipeline is expected to be delayed because the project would cut across the habitat of the federally protected Indiana bat.
机译:耗资4000万美元的24英寸管道的建设预计将被推迟,因为该项目将穿越受联邦保护的印第安那蝙蝠的栖息地。