首页> 外文会议>14th international conference amp; exhibition on liquefied natural gas (LNG 14) >HOW TO SECURE THE PROJECT TIME SCHEDULE TAKING INTO ACCOUNT THE EXTREME COLD WINTER CONDITIONS
【24h】

HOW TO SECURE THE PROJECT TIME SCHEDULE TAKING INTO ACCOUNT THE EXTREME COLD WINTER CONDITIONS

机译:如何确保考虑极端极端冬季条件的项目时间安排

获取原文
获取原文并翻译 | 示例

摘要

The Snøhvit LNG Project will be realised on the island of Melkoya, in the proximity of Hammerfest in Northern Norway. This area has specific ambient winter conditions, where the freezing temperature together with the high Northern wind, gives a wind chill factor up to - 45°C. rnAs such, outside works are becoming unfeasible from end of October until end of March. rnThe project for the storage (4 full containment storage tanks) and send–out (3 different sets of loading arms ) of the liquefied natural gas products ( LNG , LPG and condensate ), was awarded to Tractebel Gas Engineering – Belgium SA on the 16th July , 2002, while the commissioning is scheduled for August to October 2005.rnWith respect for the extreme winter conditions, the project management decided: rn
机译:Snøhvit液化天然气项目将在挪威北部Hammerfest附近的梅尔科亚岛上实现。该地区具有特定的冬季冬季条件,在该地区,冻结温度与北方强风共同作用,使风冷系数高达-45°C。因此,从10月底到3月底,外部工程变得不可行。 rn 16月,液化天然气产品(LNG,LPG和冷凝液)的存储(4个全密闭储罐)和送出(3套不同的装卸臂)项目被授予Tractebel Gas Engineering – Belgium SA 2002年7月,计划于2005年8月至2005年10月进行调试。rn考虑到极端的冬季条件,项目管理人员决定:

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号