【24h】

RCC DAM AND ROCKFILL DAM AT THE SALUDA REMEDATION PROJECT

机译:萨鲁达整治项目的碾压混凝土坝和堆石坝

获取原文
获取原文并翻译 | 示例

摘要

Saluda Dam, part of the FERC regulated Saluda Hydroelectric Project located near Columbia, South Carolina, is being upgraded to resist a recurrence of the 1886 Charleston Earthquake. Concurrent with this upgrade is a major outage and refurbishment of the adjacent McMeekin Plant, which draws cooling water from Lake Murray, formed by Saluda Dam. The existing, semi-hydraulic fill embankment Dam was completed in 1930 and, based on current technology, is viewed as being susceptible to liquefaction during the design seismic event. Several remediation options were considered with the selected approach being a back-up berm, essentially a "Dry Dam", at the downstream toe of the existing Dam. The "Dry Dam" will consist of about 5500 feet of Rockfill and about 2300 feet of RCC. This Project is the largest active (year 2002) dam construction project in the United States and the final Project will involve the placement of 1.3 million cubic yards of RCC and 3.5 million cubic yards of Rock Fill. This paper presents an overview of the design aspects of the RCC Dam and the Rockfill Dam plus portions of the McMeekin Plant upgrade that have a direct impact on the Dam Remediation Project. We address topics such as the new cooling water system and ash handling systems for McMeekin and their impact on the Dam Remediation, seismic design basis, loading conditions, finite element analysis, mix design parameters, drainage and joint design, facing considerations, thermal stress analysis joint spacing, and the mix design testing programs. An unusually large number of load cases had to be considered as the "fix" must consider "dry conditions" and "wet conditions" as well as the postulated condition of the existing embankment Dam after a recurrence of the 1886 Earthquake. The mix design program addresses the use of aggregate, from an on-site borrow area and the use of landfilled, waste flyash as a constituent of the RCC.
机译:Saluda大坝是FERC监管的Saluda水力发电项目的一部分,该项目位于南卡罗来纳州哥伦比亚附近,目前正在进行升级,以抵抗1886年查尔斯顿地震的再次发生。与此次升级同时进行的是对邻近的McMeekin工厂的一次大修和翻新,该工厂从Saluda大坝形成的Murray湖汲取冷却水。现有的半液压填筑路堤大坝于1930年完工,根据当前技术,在设计地震事件期间,该大坝被视为易液化。考虑了几种补救方案,选择的方法是在现有大坝的下游脚趾处使用备用护堤,本质上是“干坝”。 “干坝”将由大约5500英尺的堆石场和大约2300英尺的碾压混凝土组成。该项目是美国最大的活跃水坝建设项目(2002年),最终项目将涉及安置130万立方码的碾压混凝土和350万立方码的堆石料。本文概述了RCC大坝和Rockfill大坝的设计方面,以及对McMeekin厂进行升级的部分,这些方面对大坝整治项目具有直接影响。我们讨论的主题包括用于McMeekin的新冷却水系统和灰处理系统及其对大坝修复的影响,抗震设计基础,荷载条件,有限元分析,混合设计参数,排水和接缝设计,面临的考虑因素,热应力分析关节间距,以及混合设计测试程序。必须考虑到异常大量的工况,因为“修复”必须考虑“干燥条件”和“潮湿条件”以及1886年地震再次发生后现有堤坝的假定条件。混合料设计方案涉及现场取土区的骨料的使用,以及将垃圾填埋的废粉煤灰用作RCC的组成部分。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号