This paper addresses the control systems engineering effort required to rehabilitate instrumentation and controls for a cogeneration power plant which suffered extensive damage due to a plant fire. An extraordinary planning and coordination effort between contractors and equipment suppliers enabled the effort to be completed within a very tight, four month schedule. Contractual obligations were met when electrical power was produced in advance of the commitment date.
机译:本文涉及控制系统的控制系统工程工作,以恢复由于植物火灾遭受广泛损坏的热电联产电厂的仪器和控制。承包商和设备供应商之间的非凡规划和协调努力使努力在一个非常紧张,四个月的时间表内完成。何时在承诺日期提前生产电力时满足合同义务。