Jinlong's copper flash smelting process started up in April 1997. In the early days of production, lots of equipment and process problems were encountered. But, through continuous improvements in equipment and operation, the designed productivity was reached two years later and the smelting operation has been greatly upgraded since then. After more than 4 years of production, we have made great achievements, such as increasing the flash furnace availability, significant improvements in operation control, optimization of concentrate burner's structure and operation, and smooth operation of the whole smelter. This paper outlines Jinlong's operational achievements made after commissioning, and discusses problems that were encountered and their countermeasures. Operational experience is also summarized.