Automatically Determining the Latest Possible Equipment Installation Times for Shipbuilding

机译:自动确定用于造船的最新设备安装时间

获取原文
获取原文并翻译 | 示例

摘要

Determining the latest possible point in time during which a component can be installed is important to the efficient implementation of automatic outfitting planning methods. This point is a function of a component's size, the vessel's general arrangement, the size of the openings connecting the compartments, crane access, and the section building schedule. This paper develops a method for automatically determining component installation deadlines by modeling a vessel as a dynamic network of compartments which grows as the ship's sections are erected. A test case of a recently delivered pipelaying vessel was used to assess the developed methodology.
机译:确定可以安装组件的最新可能时间点对于有效实施自动装配计划方法很重要。这一点取决于部件的尺寸,船舶的总体布置,连接舱室的开口的尺寸,起重机的出入通道以及型材的建造时间表。本文提出了一种通过将船舶建模为动态的舱室网络来自动确定组件安装期限的方法,该网络随着舱室的竖立而增长。使用最近交付的铺管船的测试案例来评估开发的方法。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号