Delays in Gas, Oil, and Water Wells Projects

机译:天然气,石油和水井项目的延误

获取原文
获取原文并翻译 | 示例
           

摘要

An ABC company in Saudi Arabia awards to contractors many gas, oil, and water wells projects every year. It was noticed that the majority of these projects were completed beyond their contractual schedules. This study was performed to identify the extent and causes of delay in such projects. The files of 176 completed gas, oil, and water projects were studied to determine the extent of delay. Then, a thorough investigation of 20 files was performed to define the causes of delays, to measure their effect on projects schedules, and to identify the party responsible for the delays. It was possible to measure the extent of delay and to reveal the causes, with their roots, behind these delays. The results indicated that the causes of delays which were rooted to owners contribute more heavily to the extent of delay than those causes rooted to contractors and others. The various parties in the construction industry will benefit from the findings of this study by eliminating and/or mitigating the effects of the identified causes of delays from their current and future projects.
机译:沙特阿拉伯的一家ABC公司每年都会向承包商授予许多天然气,石油和水井项目。值得注意的是,这些项目大多数都超出了合同时间表。进行这项研究是为了确定此类项目延迟的程度和原因。研究了176个已完成的天然气,石油和水项目的文件,以确定延迟的程度。然后,对20个文件进行了彻底的调查,以确定延迟的原因,衡量其对项目进度的影响,并确定造成延迟的一方。可以测量延迟的程度,并揭示造成这些延迟的根源。结果表明,与造成承包商延误的原因相比,根源于所有者的延迟原因对延迟的影响更大。通过消除和/或减轻其当前和未来项目中已确定的延迟原因的影响,建筑行业的各方将受益于本研究的结果。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号