Reviewing Resource Leveled Schedules Using P6

机译:使用P6查看资源级别的时间表

获取原文
获取原文并翻译 | 示例
           

摘要

Standard CPM schedule review techniques are insufficient to review automatically resource leveled schedules. When faced with the task of reviewing resource leveling, most reviewers try to pretend that it does not exist and ignore this facet of the schedule submittal. This paper provides a guide to effective review of resource leveling that can be used on construction projects utilizing an Oracle/Primavera P6 Professional? CPM schedule. This paper also discusses a large number of issues and guidelines to be considered when evaluating an automatically resource leveled CPM schedule. Beginning with issues such as how to identify if resource leveling has been used, this paper delves into the analysis of the root causes of resource delay and techniques for separating reality from error. Causes for rejection of a resource leveling procedure are covered. Methods for validating how well the plan was executed are explained. Using these procedures, the reviewer can potentially know more about the resource leveled schedule than the person who submitted it.
机译:标准CPM计划审查技术不足以审查自动资源级别的计划。当面对审查资源调平的任务时,大多数审阅者都试图假装它不存在并忽略所提交的时间表的这方面。本文为利用Oracle / Primavera P6专业人员提供了可用于建筑项目的资源调平有效审查指南CPM计划。本文还讨论了在评估自动资源级别的CPM计划时考虑大量问题和指南。从诸如如何识别资源级别的问题的问题开始,本文涉及资源延迟和从错误分离现实的技术的根本原因分析。覆盖了拒绝资源调平程序的原因。解释了验证计划执行的方法。使用这些程序,审阅者可能更多地了解资源划分的时间表,而不是提交它的人。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号