Piedras Verdes: Mexico's newest copper mine

机译:Piedras Verdes:墨西哥最新的铜矿

获取原文
获取原文并翻译 | 示例
           

摘要

It took FCC approximately four years and six months from the time that it acquired Phelps Dodge's 70 percent interest in the project until commencement of copper production. During this period, an agreement had to be entered into with the Piedras Verdes Ejido to enable the company to relocate the inhabitants of the old village to the new townsite approximately 6 km (3.7 miles) to the south. A reliable underground water supply was discovered and permitted approximately 6 km (3.7 miles) east of the mine. Surface rights required for openpit mining, processing and heap leaching operations had to be purchased or leased from the four Ejidos and private land owners in the area and an acceptable contract had to be negotiated for mining services.Many months of hard work by company employees and consultants were spent ensuring that the various federal, state and municipal permits were obtained before to the commencement of mining and construction activities. Once all of the permits were in place, the Piedras Verdes project and associated infrastructure were constructed and commissioned in 12 months at a capital cost of 100 million US dollars.
机译:从FCC收购菲尔普斯道奇(Phelps Dodge)在该项目中的70%股权到开始生产铜,大约用了四年零六个月的时间。在此期间,必须与Piedras Verdes Ejido签订协议,以使公司能够将旧村庄的居民迁移到新城镇,距南部约6公里(3.7英里)。发现了可靠的地下水供应,并允许其位于矿井以东约6公里(3.7英里)处。必须从该地区的四个Ejidos和私人土地所有者处购买或租赁露天采矿,加工和堆浸操作所需的地面使用权,并且必须就采矿服务达成可接受的合同。公司员工和花费顾问来确保在采矿和建筑活动开始之前已获得各种联邦,州和市政许可证。一旦所有许可证都到位,Piedras Verdes项目和相关基础设施便在12个月内建成并投入使用,资本成本为1亿美元。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号