Application of fuzzy set theory to project scheduling of bridge construction

机译:模糊集理论在桥梁施工项目调度中的应用

获取原文

摘要

The present research treats various kinds of uncertainties which influence the activity duration for each separate erection process in terms of fuzzy sets. Then, the necessary number of days for the completion of the erection can be obtained as fuzzy quantities by using fuzzy reasoning. On the basis of the fuzzy performance evaluation and review technique (PERT) network thus obtained, linear programming is used to calculate the overall project duration and its certainty. As a simple numerical example, the erection of a simple girder bridge is considered.
机译:本研究根据模糊集来处理影响每种独立安装过程的活动持续时间的各种不确定性。然后,可以通过使用模糊推理获得完成安装所需的天数作为模糊量。在由此获得的模糊绩效评估和审查技术(PERT)网络的基础上,使用线性规划来计算总体项目工期及其确定性。作为一个简单的数值示例,考虑了一个简单的梁桥的架设。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号