Condition monitoring at Cauldon Works cement plant in the Staffordshire Moorlands (between Derby and Stoke) had indicated wear-and-tear to the intermediate and final wheel shaft and the need to re-bore and re-line the case for the raw material mill drive. The work was scheduled during a plant maintenance shutdown in January 2009 - in an eleven-day window - and the gearbox was shipped back to David Browns Park Works in Huddersfield. This timescale became more challenging when the logistical difficulties of removing such a large piece of equipment led to a two-day delay.
机译:斯塔福德郡高地(Derby和Stoke之间)的Cauldon Works水泥厂的状态监测表明,中间轮轴和最终轮轴的磨损,并且需要重新打孔并重新排列原料磨机驱动装置的外壳。这项工作计划在2009年1月关闭工厂维护期间-在一个为期11天的窗口中进行-并将变速箱运回哈德斯菲尔德的David Browns Park Works。当拆除这么大设备的后勤困难导致两天的延误时,这个时间表变得更具挑战性。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号